Environmental Issues
Public registers
POEO Public Register
Licences, applications and notices search
Penalty notices search
Enforceable undertakings search
Enforceable undertakings media releases
Exemptions and approvals search
Prosecutions or civil proceedings search
Terms of use: POEO public register
Licensing FAQs
List of licences
Unlicensed premises regulated by the EPA
Contaminated land record of notices
About the record of notices
List of notified sites
Tips for searching
Disclaimer
Dangerous goods licences
Pesticide licences
Radiation licences
Home
Public registers
POEO Public Register
Licences, applications and notices search
Non-Compliance detail
Summary
Licence number:
4848
Annual Return Start:
17 Aug 2002
Annual Return End:
16 Aug 2003
Date Received:
14 Oct 2003
Licence Condition number
Type of non-compliance
EPA actions
No. of times occurred
L3.1
Weekly analysis of discharge to Murray River showed 1 breach of pH limit, 12 exceedances of TSS limit, 3 exceedances of BOD limit, 5 exceedances of NOx-N limit and 6 exceedances of total N limit.
N/A
N/A
L3.1
Analysis of weekly samples to Murray River revealed 12 exceedances of Pb limit.
N/A
N/A
M2.1
Licensee failed to monitor points 8 & 9 as required by the licence
N/A
N/A
M2.1
Licensee failed to monitor point 11 in accordance witjh the licence.
N/A
N/A
M2.1
Licensee failed to monitor point 14 in accordance with licence.
N/A
N/A
M2.1
Licensee failed to monitor points 18 - 21 in accordance with the licence.
N/A
N/A
M2.1
Licensee failed to monitor points 7, 44-56, 58-60 in accordance with the licence.
N/A
N/A
M2.1
Licensee failed to monitor point 26 in accordance with the licence.
N/A
N/A
L3.1
SOx emissions from points 36 & 37 (boiler stacks) exceeded licence limit.
N/A
N/A
L3.1
Stack sampling results for NOx from point 61 (TNT denitrification scrubber) were in excess of licence limit.
N/A
N/A